General Outage Information

Generation Outages

EirGrid and SONI develop and implement a Generation Outage Plan. This ensures co-ordination of  “planned outages”, when power stations will not be available due to maintenance or other reasons.

The Generation Outage Plan takes into account security of supply in Ireland and Northern Ireland, as well as economic operation of the power systems, and the maintenance/resource needs of generators.

For more information on Generation Outage planning or requesting a Generator Outage, please go to Generation Outages. This page also contains the latest outage documents and guidelines.

Transmission Outages

The Power System Operational Planning section (PSOP) in EirGrid puts together a Transmission Outage Programme and manages transmission outages. This involves planned times when transmission infrastructure (lines, cables and substations etc.) will be out of service for maintenance. It also involves times when testing, connection of new plant and decommissioning of old plant is carried out.

Transmission maintenance takes place in line with the EirGrid Asset Maintenance Policy to ensure that the transmission system can operate in a safe, secure and reliable manner. A Guide to Transmission Equipment Maintenance is available here.

A high level description of the transmission outage planning process is available here.

For more information on transmission outage planning or requesting a transmission customer outage, visit the transmission outages page.

For information on the availability of Generators, please go to our library and search 'Availability Reports'.

Outturn Availability

The Single Electricity Market Committee (SEMC) decision SEM-15-071 "Process for the Calculation of Outturn Availability" was published on 29 September 2015.

For information relating to the process for the calculation of outturn availability, please see The EirGrid and SONI Implementation Approach to the SEM Committee Decision Paper SEM-15-071.

The Ireland Ex-Ante Outturn Availability Connection Asset Annual Maintenance Plan for the 2016 outage season, as approved by the Regulatory Authorities, is published here.

The Ireland Ex-Post Outturn Availability Connection Asset Annual Maintenance Plan for the 2016 outage season, as approved by the Regulatory Authorities, is published here.

The Ireland Ex-Ante Outturn Availability Connection Asset Annual Maintenance Plan for the current outage season, as approved by the Regulatory Authorities, is published here.

REMIT Publications

EirGrid will now be sending out updates (via email) to the REMIT publication in the event that there is a significant change to the outage schedule. If market participants wish to be included in an email distribution list, please let EirGrid know by emailing psop@eirgrid.com. Note that these emails will only be sent during normal office hours.

Regulation on Wholesale Energy Markets Integrity and Transparency (REMIT) is a new EU Regulation (# 1227/2011) which establishes a new framework for the integrity and monitoring of the wholesale energy market. Under REMIT, market participants are obliged to fulfil the obligations described in Article 4 (1) specifically that “Market participants shall publicly disclose in an effective and timely manner inside information which they possess...”

EirGrid and SONI will now publish detailed generator and interconnector unit outage plan updates in a more regular and timely manner to improve transparency and assist market participants in complying with REMIT in this regard.

Thus, in addition to the annual All-Island Outage Plan updated quarterly and the 2-month All-Island Outage Plan published monthly, a new weekly All-Island Outage Plan covering the next 16 weeks will be published here. The report consists of two worksheets; the first sheet shows the outages graphically at a daily level and the second worksheet shows the start and finish times and dates of the outages. Outages are represented with an abbreviation in the files - “S” represents a Scheduled Outage and “F” represents a Forced Outage.

Outage Week 26(2018)-41(2018) - Published on 20 June 2018

Outage Week 25(2018)-40(2018) - Published on 13 June 2018

Outage Week 24(2018)-39(2018) - Published on 06 June 2018

Outage Week 23(2018)-38(2018) - Published on 30 May 2018

Outage Week 22(2018)-37(2018) - Published on 23 May 2018

Outage Week 21(2018)-36(2018) - Published on 16 May 2018

Outage Week 20(2018)-35(2018) - Published 09 May 2018

Outage Week 19(2018)-34(2018) - Published 02 May 2018

All-Island Outage Plan publications for previous weeks can be found in our Library.

Interconnector Information

Forced Outage

  • The East West Interconnector will be on a forced outage from 09 May 2018 18:00 until 12 May 2018 05:59.

Black Start Testing

  • The East West Interconnector will be undergoing Black Start Testing on 14 May 2018 from 06:00 to 18:00.