Connections and contracts

09 October 2015

The connection offer process and group processing approach

SmartrGrid, Presentation by Ciara Corby, EirGrid, Customer Conference 2012.

09 October 2015

EirGrid Smart grid programme and demonstration projects

Outage_Weeks_42(2015)-04(2016)

07 October 2015

Outage_Weeks_42(2015)-04(2016)

Windfarm Performance Monitoring Process - October 2015

01 October 2015

Windfarm Performance Monitoring Process - October 2015

Explanatory Paper for Transmission Loss Adjustment Factor (TLAF) Calculation Methodology

01 October 2015

This document is an explanation or methodology of how Transmission Loss Adjustment factors are calculated step by step.

Powerpoint Presentation on Towers

01 October 2015

Presentation shows different array of towers including IVI Design, VVV Design and Inverted Delta Design

APPENDIX A Approach to the Development of Electricity Transmission Lines

01 October 2015

The purpose of this document is to provide information as to how we progress our large-scale transmission infrastructure projects over a number of key stages - through the public planning process, to construction and eventual operation.

Project development and Consultation Road Map

01 October 2015

Project development and Consultation Road Map showing stages 1 to 5

Map showing route corridors (no title)

01 October 2015

Map showing Route corridor A, 3B, preferreded route corridor for the Northern portion of the 400kV OHL, exisitng 220kV OHL and Indicative 400kV Line Route

Tarbert 220kV Substation Redevelopment Proposed Overhead Line & Cable Route Diversion - Figure 4 Map

01 October 2015

A3 Tarbert 220kV Substation Redevelopment Proposed Overhead Line & Cable Route Diversion - Figure 4 Map AT SCALE 1:10,000