Donegal 110kV

This project is a joint development between ESB Networks and EirGrid, the first part of which is now complete.

This page shows you information on this project's activity, with more recent news first.

October 2019

The final part of this project was completed by ESB Networks in Q3 2019. This involved a new 110 kV station along the Binbane to Letterkenny line at Tievebrack and a new 110 kV distribution line to a new station at Ardnagappary.

2017

The first part of this project, a new 110 kV transmission line from Binbane to Letterkenny, was energised in 2014.

The second part of this project, a new 110 kV distribution line from Ardnagappary to Tievebrack, is being developed by ESB Networks. It is under construction and is due to be completed in Q2 2019.