EirGrid

European Integration Consultations

Consultations are held prior to the submission of proposed new local, regional and European rules.

Consultations

Local consultations related to the Network Codes are shown below. For European and Regional consultations please visit the ENTSO-E consultation hub

EBGL – Article 18 Local Terms and Conditions Proposal Consultation

21.08.20 Commission Regulation (EU) 2017/2195, establishing a guideline on electricity balancing (EBGL), entered into force on 18th December 2017. Under Article 64, Ireland and Northern Ireland had a derogation on aspects of this Guideline other than those related to participation in development of terms and conditions or methodologies, until 31st December 2019.

Article 18 of EBGL outlines a requirement for TSOs to develop a proposal for terms and conditions for balancing service providers, balance responsible parties, and central dispatch model specific conditions. Article 5 of EBGL outlines a requirement for a proposal for these terms and conditions to be approved by the relevant Regulatory Authority (RA). Article 10 outlines a requirement for TSOs to carry out a public consultation on the proposal for local terms and conditions for at least one month, and for justification for including or not including the feedback from stakeholders to be included in the submission to the RA.

EirGrid and SONI have today published for consultation the proposal for terms and conditions under Article 18 of EBGL. The document being consulted on is here. This consultation runs from 21/08/2020 to 5pm close of business on 21/09/2020. Please email your submission to Martin.Kerin@EirGrid.com or Christopher.Goodman@soni.ltd.uk with the subject title “EBGL – Article 18 Local Terms and Conditions Proposal Consultation”. Please indicate within your submission if you wish for it to be treated confidentially.

SOGL – Coordinated Security Analysis (CSA) Consultation – (Ireland & United Kingdom)

15.07.20. The Regulatory Authorities of the IU Capacity Calculation Region have approved the IU ROSC (Regional Operational Security Coordination Methodology) on 18 June 2020.

RA Revisions on IU ROSC Methodology

Final approved IU ROSC Methdology

18.02.20 No industry comments were received to the consultation. Informal comments were received from the CRU and were incorporated into the draft. EirGrid, SONI and NGESO submitted the following to their respective regulatory authorities on 18 December 2019.

IU ROSC (Regional Operational Security Coordination Methodology) 

Explanatory note to the IU ROSC

10.10.19 Article 75 and 76 of Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (SOGL) pertain to Coordinated Security Analysis.  Following on from the ACER decision on the Coordinated Security analysis methodology in June, EirGrid, SONI and National Grid ESO have developed a draft CSA methodology for the Ireland United Kingdom (IU) Capacity Calculation Region (CCR). All three TSOs are consulting on this draft methodology from October 11th until November 11th. Please find the draft methodology here and an explanatory note here. Responses should be sent to gridcode@eirgrid.com by end of day 11 November 2019. Note all responses will be shared with all three TSOs and all three National Regulatory Authorities, and may be published. If you would prefer your response not to be published please mark it confidential.

Key Organisational Requirements, Roles and Responsibilities SGU Consultation – Ireland 

25.01.2019 On the 14th September 2017, the Commission Regulation (EU) 2017/1485 establishing a guideline on electricity transmission system operation (SO GL) entered into force. Article 40(6) of SO GL required all TSOs to agree on Key Organisational Requirements, Roles and Responsibilities (KORRR) relating to Data Exchange. KORRR was approved by the All Regulatory Authority on 19th December 2018, and will serve as the basis for what TSOs, DSOs and Significant Grid Users (SGUs) will need to do to comply with Articles 41 to 53 of SO GL. TSOs, DSOs and SGUs will need to comply with KORRR from 14th March 2019.

SGUs are the target audience of this consultation. SGUs are as defined under Article 2(1) of SO GL, which are;

(a) existing and new power generating modules that are, or would be, classified as type B, C and D in accordance with the criteria set out in Article 5 of Commission Regulation (EU) 2016/631;

(b) existing and new transmission-connected demand facilities;

(c) existing and new transmission-connected closed distribution systems;

(d) existing and new demand facilities, closed distribution systems and third parties if they provide demand response directly to the TSO in accordance with the criteria in Article 27 of Commission Regulation (EU) 2016/1388;

(e) providers of redispatching of power generating modules or demand facilities by means of aggregation and providers of active power reserve in accordance with Title 8 of Part IV of SO GL; and

(f) existing and new high voltage direct current (‘HVDC’) systems in accordance with the criteria in Article 3(1) of Commission Regulation (EU) 2016/1447.

The requirements of KORRR apply to new and existing SGUs.

Under Article 40(5) of SO GL, the TSO is required to co-ordinate with DSOs and SGUs within its Observability Area on the applicability and scope of data exchange. Also, under Article 40(7) each TSO is to reach an agreement with relevant DSOs on the processes and formats of data exchange between them. The purpose of this consultation is:

To define the TSO’s and DSO’s proposed applicability and scope of KORRR.

To enable the accurate incorporation of SGU interactions under KORRR to the TSO-DSO agreement.

To provide SGUs with clear information of the TSO’s and DSO’s proposed SGU commitments under KORRR, and a mechanism for SGUs to provide feedback to the TSO and DSO ahead of the TSO-DSO agreement in March 2019

Current data exchange practices are already largely aligned with KORRR. As a result, the proposals in this KORRR consultation align with current practices and the requirements of the Grid Code and Distribution Code. EirGrid is seeking your feedback on a number of proposals which reflect this, with the below documents available for download:

KORRR SGU Consultation – Ireland

KORRR 

KORRR SGU Consultation Response Template – Ireland

The consultation runs from 25 January 2019 to 17:00 close of business 25 February 2019 inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Commission for Regulation of Utilities. A response template has been provided to facilitate this feedback (see number 3 above). Please email your submission by 17:00 25 February 2019 to gridcode@eirgrid.com with the subject title “KORRR SGU Consultation”.

This proposal document is produced jointly by EirGrid in its role as the Transmission System Operator in Ireland and ESB Networks in its role as the Distribution System Operator in Ireland.

SONI Ltd. in its role as the Transmission System Operator in Northern Ireland and NIE Networks in its role as the Distribution Network Operator in Northern Ireland are holding a similar consultation with SGUs in Northern Ireland.

Electricity Emergency and Restoration Consultation – Ireland

17/02/2022 CRU decision paper on Test Plan Proposal for Ireland 

Following the below Test Plan consultation and submission, the Commission for the Regulation of Utilities issued a decision paper on 17 February 2022. It is available to download here. The final Test Plan proposal document, as submitted, can be found here.

07/05/2021 The below Test Plan Consultation is now closed. 

09/04/2021 EirGrid Public Consultation on Test Plan Proposal

Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

Consequential to a number of requirements mandated by NCER, EirGrid is seeking your feedback on the Proposal for Test Plans for Ireland. This document is available for download:

1. Test Plan Proposal for Ireland – For Consultation

The consultation runs from 09 April 2021 to 07 May 2021 at 5pm inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Commission for Regulation of Utilities. A response proforma has been provided to facilitate this feedback (within document 1 above). Please email your submission by 17.00 on 07 May 2021 to gridcode@eirgrid.com with the subject title “Test Plan Consultation - Ireland”.

19/02/2021 EirGrid submitted the below following proposal documents to the Commission for the Regulation of Utilities on 16 October 2020.

System restoration plan for Ireland

System defence plan for Ireland

The terms and conditions to act as a restoration service provider for Ireland

The terms and conditions to act as a defence service provider for Ireland

The rules for the suspension and restoration of market activities for Ireland

Definition of Significant Grid User Ireland

The Commission for the Regulation of Utilities issued a decision paper on 10 February 2021. It is available to download here.

21/08/2020 This consultation is now closed.

07/08/2020 Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

The below consultation published on 08/07/2020 is being extended in order to allow for further stakeholder responses.

The consultation will now close at 5pm close of business Friday 21 August 2020.

Please email your submission by 17.00 on 21 August 2020 to gridcode@eirgrid.com or for any material related specifically to Distribution System Operation, to DSOGenerators@esb.ie, with the subject title “Emergency and Restoration Consultation - Ireland”.

08.07.2020 Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

Consequential to a number of requirements mandated by NCER, the TSO (EirGrid) and DSO (ESB Networks) are seeking your feedback on a number of documents. The documents are available for download:

System restoration plan for Ireland re-submission 

System defence plan for Ireland re-submission

The terms and conditions to act as a restoration service provider for Ireland re-submission 

The terms and conditions to act as a defence service provider for Ireland re-submission

The rules for the suspension and restoration of market activities for Ireland re-submission 

Response proforma re-submission

The consultation runs from 8 July 2020 to 5pm close of business 7 August 2020 inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Commission for Regulation of Utilities. A response proforma has been provided to facilitate this feedback (see document 6 above). Please email your submission by 17.00 on 7 August 2020 to gridcode@eirgrid.com or for any material related specifically to Distribution System Operation, to DSOGenerators@esb.ie, with the subject title “Emergency and Restoration Consultation - Ireland”.

02.09.2019 The Commission for Regulation of Utilities issued a decision paper, it is available to download here

18.12.2018 EirGrid submitted the following proposal documents to the Commission for Regulation of Utilities:

System restoration plan for Ireland 

System defence plan for Ireland

The terms and conditions to act as a defence and restoration service provider for Ireland 

The rules for the suspension and restoration of market activities for Ireland 

14.12.2018 Consultation closed.

14.11.2018 Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

Consequential to a number of requirements mandated by NCER, EirGrid is seeking your feedback on a number of documents. The documents are available for download:

System restoration plan for Ireland 

System defence plan for Ireland 

The terms and conditions to act as a defence and restoration service provider for Ireland

The rules for the suspension and restoration of market activities for Ireland 

Response proforma

The consultation runs from 14 November 2018 to 5pm close of business 13 December 2018 inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Commission for Regulation of Utilities. A response proforma has been provided to facilitate this feedback (see document 5 above). Please email your submission by 17.00 on 13 December 2018 to gridcode@eirgrid.com with the subject title “Emergency and Restoration Consultation - Ireland”.

Electricity Emergency and Restoration Consultation – Northern Ireland

08/02/2022 UR decision paper on Test Plan Proposal for Northern Ireland 

Following the below Test Plan consultation and submission, the Utility Regulator issued a decision paper on 8 February 2022. It is available to download here. The final Test Plan proposal document, as submitted, can be found here.

07/05/2021 The below Test Plan Consultation is now closed.

09/04/2021 SONI Public Consultation on Test Plan Proposal

Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

Consequential to a number of requirements mandated by NCER, SONI is seeking your feedback on the Proposal for Test Plans for Northern Ireland. This document is available for download:

1. Test Plan Proposal for Northern Ireland – For Consultation

The consultation runs from 09 April 2021 to 07 May 2021 at 5pm inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Utility Regulator. A response proforma has been provided to facilitate this feedback (within document 1 above). Please email your submission by 17.00 on 07 May 2021 to gridcode@soni.ltd.uk with the subject title “Test Plan Consultation – Northern Ireland”.

19/02/2021 SONI submitted the below following proposal documents to the Utility Regulator on 16 October 2020.

System restoration plan for Northern Ireland

System defence plan for Northern Ireland

The terms and conditions to act as a restoration service provider for Northern Ireland

The terms and conditions to act as a defence service provider for Northern Ireland

The rules for the suspension and restoration of market activities for Northern Ireland

Definition of Significant Grid User Northern Ireland

The Utility Regulator issued a decision paper on 12 February 2021. It is available to download here.

21/08/2020 This consultation is now closed.

03/07/2020 Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NCER) aims to maintain operational safety and prevent the spread of an incident on the electricity network that could result in a widespread failure.

Consequential to a number of requirements mandated by NCER, SONI is seeking your feedback on a number of documents. The documents are available for download:

System restoration plan for Northern Ireland re-submission

System defence plan for Northern Ireland re-submission

The terms and conditions to act as a restoration service provider for Northern Ireland re-submission

The terms and conditions to act as a defence service provider for Northern Ireland re-submission

The rules for the suspension and restoration of market activities for Northern Ireland re-submission

Response proforma re-submission

The consultation runs from 8 July 2020 to 5pm close of business 21 August 2020 inclusive.

We look forward to receiving your feedback and will use it to inform our submissions to the Commission for Regulation of Utilities. A response proforma has been provided to facilitate this feedback (see document 6 above). Please email your submission by 17.00 on 21 August 2020 to gridcode@soni.ltd.uk with the subject title “Emergency and Restoration Consultation – Northern Ireland”.

HVDC Consultation on Parameter Selection – Ireland

12.10.2020 The Commission for Regulation of Utilities issued a decision paper, it is available to download here.

04.02.2019 EirGrid submitted our Proposal for the General Application of the HVDC Requirements for Ireland to the Commission for Regulation of Utilities on 21 December 2018.

08.12.2018 Consultation closed.

09.11.2018 The Network Code HVDC Code is one of three Connection Codes which form part of the European Network Codes. It seeks to provide a clear legal framework for grid connections and facilitate electricity trading whilst ensuring system security, facilitating the integration of HVDC connections, including DC-connected Power Park Modules, as well as the associated system services while ensuring a more efficient use of the network.

HVDC ‘entered into force’ on 15 September 2016, and applies to high voltage direct current systems and direct current-connected power park modules that conclude a final and binding contract for the purchase of their main plant after 15 September  2018.

As part of the national implementation of HVDC, the relevant TSO of each member state needs to submit a proposal for requirements of general application. It is not a requirement of HVDC to consult upon the proposal for requirements of general application prior to submission to the CRU. The TSO is issuing this consultation document in the interest of transparency and to ensure that the TSO has the best information available to them to submit an appropriate set of recommendations to the CRU for the proposal of requirements of general application.

We look forward to receiving your feedback and using it to improve our proposal. A template has been provided to facilitate this feedback. Please email your submission by 7 December 2018 to GridCode@eirgrid.com with the subject title “HVDC Consultation on Parameter Selection - Ireland”.

Download the consultation document here

Download the response template here

HVDC Consultation on Parameter Selection – Northern Ireland

26.06.19 The Utility Regulator issued a decision paper, it is available to download here.

04.02.2019 SONI submitted our Proposal for the General Application of the HVDC Requirements for Northern Ireland to the Utilities Regulator on 21 December 2018.

08.12.2018 Consultation closed.

09.11.2018 The Network Code HVDC Code is one of three Connection Codes which form part of the European Network Codes. It seeks to provide a clear legal framework for grid connections and facilitate electricity trading whilst ensuring system security, facilitating the integration of HVDC connections, including DC-connected Power Park Modules, as well as the associated system services while ensuring a more efficient use of the network.

HVDC ‘entered into force’ on 15 September 2016, and applies to high voltage direct current systems and direct current-connected power park modules that conclude a final and binding contract for the purchase of their main plant after 15 September  2018.

As part of the national implementation of HVDC, the relevant TSO of each member state needs to submit a proposal for requirements of general application. It is not a requirement of HVDC to consult upon the proposal for requirements of general application prior to submission to the Utility Regulator. The TSO is issuing this consultation document in the interest of transparency and to ensure that the TSO has the best information available to them to submit an appropriate set of recommendations to the Utility Regulator for the proposal of requirements of general application.

We look forward to receiving your feedback and using it to improve our proposal. A template has been provided to facilitate this feedback. Please email your submission by 7 December 2018 to gridcode@soni.ltd.uk  with the subject title “HVDC Consultation on Parameter Selection – Northern Ireland”.

Download the consultation document here

Download the response template here

Consultation for Ireland/Northern Ireland – Synchronous Area Operational Agreement (SOGL Art.118) and LFC Block Operational Agreement (SOGL Art.119)

19.10.2022 Updated SAOA and LFCBOA as of 20/10/2022.

06.02.20 The final documents can be found here:SAOA and LFCBOAThey come into force on 15/2/20. 

09.01.20 The CRU and Utility Regulator published their Approval on the Title 2 methodologies of the SAOA and LFCBOA which can be found here and here.

15.11.19 The CRU and Utility Regulator published their Decision on the proposed Title 2 methodologies of the SAOA and LFCBOA which can be found here and here.

26.08.19 EirGrid and SONI submitted amended proposals on Title 2 of the SAOA and LFCBOA to their respective Regulatory Authorities on 23.08.19. Further amendments were made to Title 1 and title 3 of both documents; however these do not require regulatory approval. The updated SAOA can be downloaded here and the updated LFCBOA can be downloaded here.

14.08.19 Consultation is now closed

15.07.19 Following the Regulatory Authorities’ Request for Amendment (RfA) on the submitted SAOA and LFCBOA, EirGrid and SONI have updated the documents. EirGrid and SONI are now carrying out a one month consultation on the revised versions and welcome any feedback, in particular on Title 2 of each document. The updated SAOA can be found here and the updated LFCBOA can be found here. Responses to the consultation should be sent to gridcode@eirgrid.com or gridcode@soni.ltd.uk by 17h00 on Wednesday 14.08.2019. Responses will be shared with the Regulatory Authorities and may be published on our websites. Please indicate if you would prefer for your response not to be published.

24.6.19 The CRU and Utility Regulator published their Request for Amendment to the proposed SAOA and LFCBOA which can be found on the CRU website here and the Utility Regulator website here.

24.01.19 EirGrid and SONI submitted draft proposals on the SAOA and LFCBOA to their respective Regulatory Authorities on 21.12.18. The draft SAOA can be downloaded here and the draft LFCBOA can be downloaded here.

09.11.18 Consultation is now closed.

09.10.18 This consultation concerns the EirGrid and SONI proposals relevant to Ireland and Northern Ireland for the Synchronous Area Operational Agreements (SAOA) and the LFC Block Operational Agreements (LFCBOA). These have been developed in accordance with Articles 118 and 119 respectively of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (SOGL).

SOGL requires that TSOs of each synchronous area responsible for operating load frequency control and reserves, which for Ireland is EirGrid, and for Northern Ireland is SONI, should develop SAOA and LFCBOA.

The SAOA and LFCBOA are contained in two respective documents with text relative to the legal articles.  These documents aim at presenting operational rules from Ireland and Northern Ireland according to the pan-EU framework, thereby facilitating greater cross-border cooperation in matters of security and the development of cross-border balancing services in terms of sharing and exchange of reserves.

Why are we consulting?

SOGL Articles 118 and 119 methodologies that are also referenced in SOGL articles 6(3)(d), 6(3)(e) and article 11 must have a statutory public consultation prior to National Regulatory Authority approval.  These are Title 2 Articles in the SAOA and LFCBOA documents.

Link to the Consultation

The consultation was launched on the ENTSO-E website on 08 October 2018. The consultation papers and the response details are hosted on the ENTSO-E website located here. Responses to the consultation should be sent to gridcode@eirgrid.com by 17h00 on 08 November 2018.

DCC Consultation on Parameter Selection – Ireland

12.09.19 The Commission for Regulation of Utilities issued a decision paper, it is available to download here .

01.10.18 EirGrid submitted our Proposal for the General Application of the DCC Requirements for Ireland to the Commission for Regulation of Utilities on 20 September 2018.

06.07.2018 The Network Code Demand Connection Code is one of three Connection Codes which form part of the European Network Codes. It seeks to provide a clear legal framework for grid connections and facilitate electricity trading whilst ensuring system security, facilitating the integration of demand side system services and ensuring a more efficient use of the network.

DCC ‘entered into force’ on 7 September 2016, and applies to demand Units, demand facilities, distribution systems and closed distribution systems that conclude a final and binding contract for the purchase of their main plant after 7 September  2018.

As part of the national implementation of DCC, the relevant TSO of each member state needs to submit a proposal for requirements of general application. It is not a requirement of DCC to consult upon the proposal for requirements of general application prior to submission to the CRU. The TSO and DSO are issuing this consultation document in the interest of transparency and to ensure that the TSO and DSO have the best information available to them to submit an appropriate set of recommendations to the CRU for the proposal of requirements of general application

We look forward to receiving your feedback and using it to improve our proposal. A template has been provided to facilitate this feedback. Please email your submission by 10 August 2018 to gridcode@eirgrid.com with the subject title “DCC Consultation on Parameter Selection - Ireland”.

Download the consultation document here.

Download the response template here.

DCC Consultation on Parameter Selection – Northern Ireland

09.04.19 The Utility Regulator issued a decision paper, it is available to download here.

01.10.18 SONI and NIE Networks submitted our Proposal for the General Application of the DCC Requirements for Northern Ireland to the Utilities Regulator on 21 September 2018.

06.07.2018 The Network Code Demand Connection Code is one of three Connection Codes which form part of the European Network Codes. It seeks to provide a clear legal framework for grid connections and facilitate electricity trading whilst ensuring system security, facilitating the integration of demand side system services and ensuring a more efficient use of the network.

DCC ‘entered into force’ on 7 September 2016, and applies to demand Units, demand facilities, distribution systems and closed distribution systems that conclude a final and binding contract for the purchase of their main plant after 7 September  2018.

As part of the national implementation of DCC, the relevant TSO of each member state needs to submit a proposal for requirements of general application. It is not a requirement of DCC to consult upon the proposal for requirements of general application prior to submission to the UR. The TSO and DSO are issuing this consultation document in the interest of transparency and to ensure that the TSO and DSO have the best information available to them to submit an appropriate set of recommendations to the UR for the proposal of requirements of general application

We look forward to receiving your feedback and using it to improve our proposal. A template has been provided to facilitate this feedback. Please email your submission by 10 August 2018 to gridcode@soni.ltd.uk with the subject title “DCC Consultation on Parameter Selection - Northern Ireland”.

Download the consultation document here.

Download the response template here.

RfG Consultation on Parameter Selection – Ireland

26.11.2018 Commission for Regulation of Utilities issued a Decision Paper, it is available to download here.

16.05.2018 EirGrid and ESB Networks submitted our ‘Proposal for the General Application of the RfG Requirements for Ireland’ to the Commission for Regulation of Utilities on 16 May 2018. 

Download the proposal document here.

13.02.2018 The TSOs and DSOs have received a number of requests for an extension to the consultation deadline. As this is the first major Network Code consultation for the implementation of the Connection Codes, we have decided to extend the deadline by an extra week until Friday 16th of February.

17.01.2018 EirGrid and ESB Networks updated the consultation document with a number of clarifications:

RfG Parameter Consultation Ireland Updated with Clarifications RED LINE VERSION 

RfG Parameter Consultation Ireland Updated with Clarifications GREEN LINE VERSION 

16.01.2018 To facilitate public engagement on the RfG Consultation on Parameter Selection – Ireland, the TSO (EirGrid) and the DSO (ESB Networks) hosted an industry workshop. The slide deck is available here.

20.12.2017 (Consultation closed)

Download the consultation document here.

Download the response template here

RfG Consultation on Parameter Selection – Northern Ireland

16.11.2018 Download the Utility Regulator decision paper here.

16.05.2018 SONI and NIE Networks submitted our ‘Proposal for the General Application of the RfG Requirements for Northern Ireland’ to the Utility Regulator. Download the proposal document here.

13.02.2018 The TSOs and DSOs received a number of requests to extend the consultation deadline. As this is the first major Network Code consultation for the implementation of the Connection Codes, we decided to extend the deadline by an extra week until Friday 16th of February.

17.01.2018 SONI and NIE Networks have updated the consultation document with a number of clarifications.

RfG Parameter Consultation Northern Ireland Updated with Clarifications RED LINE VERSION

RfG Parameter Consultation Northern Ireland Updated with Clarifications GREEN LINE VERSION

11.01.2018 The slide deck from the Workshop on the RfG Consultation on Parameter Selection Northern Ireland, dated 11.01.2018, is available here.

11.01.2018 To facilitate public engagement on the RfG Consultation on Parameter Selection – Northern Ireland, the TSO (SONI) and the DSO (NIE Networks) hosted an industry workshop in Belfast. The slide deck from the Workshop on the RfG Consultation on Parameter Selection Northern Ireland, dated 11.01.2018, is available here.

20.12.2017 (Consultation closed)

Download the consultation document here.

Download the response template here.

Consultation on a proposal for the determination of LFC blocks – Ireland and Northern Ireland

29.11.2017 This public consultation is a proposal for the determination of Load Frequency Control blocks in accordance with Article 6 (3) (g) and Article 141(2) of Commission Regulation (EU) 2017/1485 establishing a guideline on electricity transmission system operation.

This public consultation document is produced jointly by EirGrid plc in its role as the Transmission System Operator in Ireland and SONI Ltd in its role as the Transmission System Operator in Northern Ireland.

This consultation applies to the synchronous area that spans Ireland and Northern Ireland.

Responses should be submitted to EirGrid and SONI at gridcode@eirgrid.com before 5pm on 8 January 2018.

Download the consultation document here.

Please find the final submitted version (dated 31 July 2018 and submitted to CRU on 10 September 2018) of the LFC Block agreement here.

The CRU approved the LFC Block Agreement on 19 November 2018. The approval document can be found on the CRU website here.

RfG Consultation on Banding Thresholds - Ireland

26.11.18 Commission for Regulation of Utilities issued a Decision Paper, it is available to download here.

15.05.18 EirGrid and ESB Networks submitted our ‘Proposal for RfG Banding Thresholds’ to the Commission for Regulation of Utilities on 15 May 2018. 

Download the proposal document here

14.07.17 The TSO has issued a Minded-To Position Paper that can be downloaded here.

07.04.17 (Consultation closed)

Download the consultation document here.

Network Codes and Guidelines

The current European Electricity Network Codes and Guidelines are as follows: